Midwest carbon-capture pipeline could be delayed after eminent domain ban in South Dakota

FILE - A sign reading "Property rights matter, no CO2" stands by a highway near Strasburg, N.D., Thursday, Jan. 11, 2024. (AP Photo/Jack Dura, File)

SIOUX FALLS, S.D. (AP) — The company behind an $8.9 billion carbon-capture pipeline proposed for five Midwestern states said Wednesday it wants to indefinitely delay its plans after South Dakota passed a law limiting its ability to acquire land for the project.

But even as it filed a to suspend its pipeline permit application timeline with the South Dakota Public Utilities Commission, the Iowa-based Summit Carbon Solutions said it remains committed to the pipeline.