Judge orders turbine manufacturer to stick with Massachusetts offshore wind farm project

FILE - Wind turbines operate at Vineyard Wind 1 offshore wind farm off the coast of Massachusetts, July 19, 2025. (AP Photo/Carolyn Kaster, File)

A Massachusetts judge on Friday temporarily blocked a turbine manufacturer from pulling out of a major offshore wind farm project, saying it would be “fanciful†to imagine a new contractor could finish the installation.

Vineyard Wind went to court last week after GE Renewables said it would be terminating its contracts for turbine services and maintenance. GE Vernova, the parent company for GE Renewables, argued that Vineyard Wind owes it $300 million for work it performed, but Vineyard Wind countered that the manufacturer remains on the hook for about $545 million to make up for a catastrophic turbine in July 2024 that set the project back by two years.